Glendale’s ‘smart meter’ billing system nearing completion

Share

This article was originally on a blog post platform and may be missing photos, graphics or links. See About archive blog posts.

All Glendale Water & Power customers will be billed next month through the 120,000 “smart meters” the utility has been installing for nearly two years, officials announced last week.

Smart meters replaced analog meters throughout the city months ago, but the utility has still been using meter readers to manually report electricity and water use as officials ensure that the system works as intended.

Advertisement

About 25% of customers are already being billed through the digital reads, but officials said that after some technology upgrades this month, the entire system will be online for billing beginning next month.

“The system does work as we expected,” said Craig Kuennen, the utility’s business transformation and marketing administrator.

Smart meters had a rough start in Glendale after opponents spoke out against them at several public meetings, claiming that the radio frequencies emitted from the devices made them sick.

Fewer have complained about the user data being collected.

On Tuesday, the City Council approved spending more than $700,000 on software and data security upgrades that would protect the personal data gathered through the digital system.

Utilities across the country are switching to smart grids in order to increase efficiencies and possibly lighten energy loads during peak times as customers curb use during high-cost periods. The U.S. Department of Energy gave Glendale $20 million of the $70 million it needed to upgrade the city’s electrical and water systems.

Through the smart grid system, Glendale residents can view their consumption through online portals.

Advertisement

Glendale Water & Power is also testing a digital photo frame that shows energy and water use on an easy-to-read display.

In a few months, the utility plans to use focus groups to analyze how pilot program participants feel about the frames, Kuennen said.

Although the billing switch will begin in January, there are still several parts of the smart grid that won’t be complete until 2014, officials said.

ALSO:

3 killed, 4 wounded in Tulare County shooting

Pedestrian killed after being struck by two cars in Palmdale

Advertisement

Police killing of grad student in dorm a ‘tragedy,’ university says

-- Brittany Levine

Advertisement